Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG - Master Project User Group

Introduction

The core technique available to Project Managers for planning and controlling their projects is Network Analysis. This short guide will provide a basic understanding of networking principles before applying them.

Network Analysis, Critical Path Analysis (CPA), or the American “Program, Evaluation, and Review Technique” (PERT) is one of the classic methods of planning and controlling the progress of projects.

Tasks or Activities

Effective planning of projects requires careful thought and the application of logic. To illustrate this planning tool, let’s consider the manufacturing process of a small item. Some typical processes might be:

  • cutting
  • finishing
  • assembling
  • purchasing
  • machining
  • testing
  • designing

All these processes are called ‘ACTIVITIES’ or ‘TASKS.’

Step 1:

List WHAT has to be done.

Hint: try thinking of verbs ending in “…ing”, like machining or testing.

Do not consider, at this stage, who is going to do what, concentrate on the WHAT only.

An activity or task is represented by a rectangle, thus:

Step 2:

Decide the ORDER in which the tasks must be done.

Some steps are obvious. We, perhaps, cannot test until assembly has been completed, which cannot be done until the various parts have been made. So, we have a logical relationship between the start of one task and the beginning of the next. We could order our list of tasks as shown:

designing   purchasing     cutting    machining   assembling    testing    finishing

Logic Network or PERT Chart

Writing this out as a network looks like this:

We put the tasks into rectangles and join them with arrows to show the sequence or precedence or the logical relationships between them.

Suppose that once we have bought the materials, some need cutting to size and others need turning on a lathe. The tasks of machining and cutting could run in parallel rather than consecutively, assuming we have the appropriate resources. But, let’s add a bit more to our process. Say the cut parts need to be welded together before assembling — like this:

Let’s add another task: the writing of a set of test instructions. Where would writing fit in? Well, the writing cannot really start until the design is finished, though it could be carried out at the same time as the fabrication. It must be ready before the testing can begin. Applying such logic to the relationships, we can add the task writing like this:

Now let’s say we need to have our draughtsman produce some illustrations for our test instructions. When the writing and the drawing are finished, we will then need to edit the whole as shown:

And, so the network is built up, often cuing the mind to missing tasks.

In this step, always assume you have infinite resources so that who does what does not cloud the issue – concentrate only on the LOGIC.

Time Analysis

Duration

Having completed the network, we can begin the analysis. Firstly, we need to know the duration of each task and write it into the network. For convenience, we will write the durations in days, as shown:

In this step, always reduce the resource requirement to the duration of ONE person to give maximum flexibility to add further resources later when the project begins to run late. There are rare cases when tasks cannot physically be performed by one resource. In which case, consider the time taken for both of them working together. For example, for carrying a very long plank that requires a person at each end, adding more resources will not necessarily reduce the duration. In fact, it might even slow it down if they get in the way of each other, but you must have two. Checking the brake lights on a car is another example.

The Forward Pass

Now we can calculate how long the project will take. We start by calculating the shortest time or ‘earliest finish.’ If we start at time ‘0,’ the earliest day that design can be finished is day 10. Purchasing; therefore, cannot start until day 10 (i.e. the earliest we can start purchasing is day 10), and thus the earliest finish for purchasing is 10 + 21 = day 31. We write the earliest start time in the top left-hand corner of the task box, and the earliest finish time over the right-hand corner of the task box.

For the purchasing task, we say the Earliest Start Time (EST) is 10 and the Earliest Finish Time (EFT) is 31.

The earliest time both cutting and machining can start is day 31. So, the earliest finish for cutting will be day 36, and for machining, day 39. However, assembly cannot start at day 39 because the welding has not yet been done. The earliest welding can start is after the cutting is finished (i.e. day 36). The earliest time assembly can start must be day 42.

Note that the task machine has some float or slack (i.e. it cannot start before day 31 and must finish before day 42, but as it only takes 8 days, there is a slack of 42 – 31 – 8 = 3 days. When calculating the earliest times, you must consider all the paths or arrows coming into the task box, and select the largest or longest time. Now if we complete the timings, or “Forward Pass” as it is called, the picture will look like this:

The calculations show that the whole project will take 52 days, or that the ‘earliest finish time’ is 52 days.

Slack

You will remember that when we considered the task machine we found that it had some slack available. You will have noted that the tasks along the paths draw, write, and edit also had some slack. The other tasks (i.e. those with no slack) are critical in that any delay in their completion will cause the whole project to be late. It is thus very important to discover the critical tasks and identify the critical path through the network.

Critical Path

The next part of the analysis of the network is to find the CRITICAL PATH. By definition the Critical Path is the shortest time path through the network. In such a simple network, it is easy to calculate the amount of slack available for each task, but in a complicated network, it is not easy to ‘see’ which tasks have slack and which have none.

The Backward Pass

So far we have calculated the Earliest Start Time (EST) and the Earliest Finish Time (EFT) for each task. The next step in calculating the critical path is to re-time the network starting at the end and calculate the Latest Start Time (LST) and Latest Finish Time (LFT) for each task.

So, beginning with the earliest finish time for the whole project (i.e. 52 days), we subtract the time of the last task giving 49 days as the latest time the finishing task can begin without affecting the outcome.

The latest time we can start testing is 49 – 2 = 47 days, and assembly in 42 days. Continuing backwards, against the arrows (doing what is called the “backward pass”), the latest time welding can start is 42 – 6 = 36 days.

But, what about cutting and machining? What is the latest time purchasing can finish? Well, the latest time machining could start is 42 – 8 = day 34, and the latest time cutting could start is 36 – 5 = day 31. Hence, the latest time purchasing can finish is day 31.

So when making the backward pass to calculate the latest times, you have to consider all the arrows coming out of a task box and select the lowest or shortest time to that task.

Now to finish the backward pass we calculate the latest times for design to finish and start. The latest time writing could start is 42 – 14 = day 28, the latest time drawing can start is 42 – 8 = 34, and the latest time purchasing can start is 31 – 21 = day 10. Therefore, the latest time design can finish without affecting the project finish time is day 10. Subtracting the time of the design task leaves us at day 0, which is back to our starting point!

Slack, Again

Now that we have completed the timings by a forward and backward pass, we can look for slack. In this simple network, it is easy to see that the tasks machine, draw, and write have slack. As we have already discovered, machining can start at day 31 but must finish by day 42. As it takes only 8 days to complete, the slack is 3 days. We will write the slack in the empty slot in the bottom center of the box. With writing, the task must finish by day 42, but it can start at day 10. As it takes 14 days to complete, writing has a slack of 24 – 42 = 18 days. Similarly, drawing has a slack of 24 days and editing 18 days. The remaining tasks have no slack at all.

The Critical Path

So, to find the critical path, we look first at the tasks who’s earliest and latest start times are identical. Then, we determine which path between such tasks has no slack. That path is, then by definition, the critical path. On the diagram below, the critical path is indicated by bold lines.

Well, there we are!

The critical path has been identified, we know the total time of the project, and we know how much slack there is in the non-critical tasks. We have a structured a plan that is logical and ordered. All we have to do now is assign resources, put it into action, and control the results!

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

A Guide to Network Analysis

Introduction The core technique available to Project Managers for planning and controlling their projects is Network Analysis. This short guide will provide a basic understanding of networking principles before applying […]

8 min read
•over 6 years ago•Updated 3 months ago•
M
Mike GlenAuthor
Project Management
Microsoft Project
Best Practices
Productivity
M
Mike Glen

Content Writer

Mike Glen from Oxfordshire, England is a Chartered Engineer and RAF pilot, who retired as a Wing Commander engineer after 32 years in the Royal Air Force. He spent eight years at Cranfield University at the Royal Military College of Science as a lecturer in project management and computer applications. Then, as a computer applications consultant for seven years, he specialized in training Microsoft Project. He was awarded MVP status in 1997 and has been re-awarded each year until 2011 (14 years). Now retired, apart from a continuing interest in computing, his spare time is taken up with four grandchildren, caravanning, visiting historic houses and gardens, serving as a lawn bowls club coach, Barbershop singing, and classical music. Mike is the co-author of Que: Special Edition Using Microsoft Project 2002 and contributor to TechTrax for Microsoft Project training. Connect with Mike as a contributor to the Microsoft Project User Group and Webmaster of the MVP Project web site at project.mvps.org.

View all articles by Mike Glen
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

The Integrated Master Plan: Terrible Name, but a Great Idea
Articles
1 min read

The Integrated Master Plan: Terrible Name, but a Great Idea

The Integrated Master Plan uses events, accomplishments, and criteria to define objective progress before scheduling begins. Here’s what it is and why it works.

A
Anonymous
11 days ago
Read
Managing the Sands of Time: How IT Projects Reflect an Hourglass
Articles
1 min read

Managing the Sands of Time: How IT Projects Reflect an Hourglass

Discover how the hourglass metaphor reveals the way time, tasks, and momentum work together in IT project management — and why managing the flow is the key to project success.

A
Anonymous
18 days ago
Read
Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown
Articles
1 min read

Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown

Ira Brown, president of Project Widgets, breaks down the four realistic migration paths, key deadlines, and a pre-migration inventory checklist to help your organization plan ahead of the September 2026 Project Online retirement.

A
Anonymous
about 1 month ago
Read
Explore All Articles