Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG - Master Project User Group

Ira H. of Northbrook, IL asks: I have a schedule for a short project where the resources are working on other projects as well. Because of this, I cant assign any of the resources to more than 15 hours per week. What is the best way to create this schedule and keep the assignments at this level of effort?

Answer: It seems that most schedulers and project managers are constantly trying to balance limited resource availability for projects. Microsoft Project can help you create this type of schedule as long as you give it all of the information that it will require. You’ll need to put the resource availability in the drivers seat to make a schedule like this work. The Project scheduling rule that will guide us is:

A project schedule is scheduled based on the PROJECT CALENDAR until a resource is assigned to the task, and then the RESOURCE CALENDAR will take over. This scheduling will occur unless a TASK CALENDAR is assigned and the resource calendar is ignored. Fixed Duration tasks are tied to dates, and resources will be scheduled between the dates of the task.

See the steps below.

1. First create calendars that will support the type of scheduling you’re trying to develop. Use the Standard calendar as the Project Calendar using the default 8-5 scheduling time. Add to the calendar any holidays that will occur during the project (Tools | Change working time).

2. After you save the changes above, make a copy of the Standard Calendar and call it “Resources 15hrs per week.” Then set the working time on this calendar to be three hours per day.

3. Assign the Standard Calendar as the Project Calendar (Project | Project Information).

4. Go to the resource sheet and View | Resource Sheet.

5. Create project resources and assign the “Resources 15hrs per week” calendar to all the resources. Make sure that the Max. Units remain at one or 100%. At this point you could update the resource calendars with vacation and unavailable days for the project.

6. Return to the Gantt Chart: View | Gantt Chart.

7.Go to Tools | Options | Calendar. Start and end times should be 9:00 a.m. and 12:00 p.m. (or whatever was chosen as the three hours per day timeframe on the calendar).

8. Set number of hours per day to three. Set number of hours per week to 15.

9. Go to Tools | Options | Schedule. Set your default task type to either Fixed Units or Fixed Work. Doing this will default each task to a task type that will allow the schedule to be developed based on resource availability. Note that for Effort-driven scheduling, either yes or no will work, but it will be yes for Fixed Work. Click OK to save the options

At this point you can enter your tasks and create your WBS. You should be estimating work on a task and not duration. The duration will be calculated at a rate of three hours per day when the resource assignment is created. I suggest creating the assignment using a split screen: View | More Views | Task Entry view. Right click in the bottom pane and select Resource Work as a view.

As the assignments are created, the timeline will move forward because the availability of the resource of the three hours per day will drive the schedule. You can view the resource assignments using the Resource Usage view. Drill into a timescale of per week per day, and you’ll see the daily assignment levels for the resources. I would also double-check for over-allocations that might have occurred as the result of assignments on multiple tasks that are concurrent. Also, if resource availability changes for the project, the resource calendars should be updated as well.

Some Considerations

Some users of Microsoft Project might have adjusted the Max. Units column to 50% or less to accomplish resource limited availability. It should be noted that Fixed Duration tasks will act differently than Fixed Unit or Fixed Work tasks under these circumstances. For example, if you have a fixed duration task that’s a two-hour meeting and a resource with a 50% Max. Unit assigned, the resource will perform 50% of the work or attend one hour of the two-hour meeting. Oops.

Another concern is that the resource name doesn’t reflect the contents of the Max. Units field. If you have varying values, assignments should be watched carefully when created, since results become more unpredictable. When Ira assigns a resource to nine hours of work, he wants it to take three days unless the resource isn’t available. The goal of Ira’s schedule is to limit the assignments to three hours per day. Allowing the resource calendars to drive the schedule is a workable solution.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Ask the Expert: Creating a Limited Resource Availability Schedule

Ira H. of Northbrook, IL asks: I have a schedule for a short project where the resources are working on other projects as well. Because of this, I cant assign […]

4 min read
•almost 17 years ago•Updated 3 months ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

The Integrated Master Plan: Terrible Name, but a Great Idea
Articles
1 min read

The Integrated Master Plan: Terrible Name, but a Great Idea

The Integrated Master Plan uses events, accomplishments, and criteria to define objective progress before scheduling begins. Here’s what it is and why it works.

A
Anonymous
9 days ago
Read
Managing the Sands of Time: How IT Projects Reflect an Hourglass
Articles
1 min read

Managing the Sands of Time: How IT Projects Reflect an Hourglass

Discover how the hourglass metaphor reveals the way time, tasks, and momentum work together in IT project management — and why managing the flow is the key to project success.

A
Anonymous
16 days ago
Read
Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown
Articles
1 min read

Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown

Ira Brown, president of Project Widgets, breaks down the four realistic migration paths, key deadlines, and a pre-migration inventory checklist to help your organization plan ahead of the September 2026 Project Online retirement.

A
Anonymous
about 1 month ago
Read
Explore All Articles