Angelo A asks: “Your mission, should you choose to accept it, is to find within Microsoft Project a cumulative resource graph over time, representing the total headcount (in total hours) of manpower (FTE or EQP) across a given project. To add to your troubles, there are resources that aren’t resources, namely the subcontract, travel, equipment numbers that are thrown in and will need to be filtered back out of the totals. A labor histogram is what would work best for us.”

Answer: I will accept this mission and do my best to answer this question. The histogram that you are looking for can be found in the Resource Usage view. This view is by resource name and you will be looking at each resource individually. Below is a view showing the head count you’re looking for. On the graph it’s called Peak Units. This value may be looked as either in the decimal or percentage — the picture below is showing the decimal view and time density per month.
Ask the Teacher: Cumulative Resource Totals in a Histogram Format
Right clicking on the boxes to the right of Peak Units will give you options to change the data available in this view. The choices may also be reached through Format | Details when in this view. Below is the same view using the cumulated work option. It’s a way of seeing the work budget over time for a resource. Cumulated cost is also available.
Ask the Teacher: Cumulative Resource Totals in a Histogram Format
To handle the “other resources” that Angelo is looking for, I suggest a totals report using the resource sheet. To obtain the breakdown by category, create a custom column with the different subtotal levels that are needed. Then create a cost table with the columns that will be needed for the report. To get accumulated subtotals, create a grouping based on the custom category column. Below is this report shown in level 1 format. (Formatting toolbar | Show | Outline Level 1). The category column doesn’t have to be on the table to get the grouping for the report.
Ask the Teacher: Cumulative Resource Totals in a Histogram Format
Mission accomplished!

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Ask the Teacher: Cumulative Resource Totals in a Histogram Format

Angelo A asks: “Your mission, should you choose to accept it, is to find within Microsoft Project a cumulative resource graph over time, representing the total headcount (in total hours) […]

2 min read
•almost 18 years ago•Updated about 1 month ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

The Compass vs. The Clock: Why Direction Beats Deadlines in Project Management
Articles
1 min read

The Compass vs. The Clock: Why Direction Beats Deadlines in Project Management

Discover why setting clear project direction matters more than chasing deadlines, and how compass-guided leadership delivers real value in project management.

A
Anonymous
8 days ago
Read
The Scripts That Save Projects: What to Say When Everything Goes Wrong
Articles
1 min read

The Scripts That Save Projects: What to Say When Everything Goes Wrong

Learn word-for-word scripts for handling scope creep, missed deadlines, executive pushback, and team performance issues as a project manager.

A
Anonymous
9 days ago
Read
How Reserves Keep Projects Alive
Articles
1 min read

How Reserves Keep Projects Alive

Learn how project reserves protect your budget and schedule from unexpected risks, including when and how to use contingency, management, schedule, and cost reserves effectively.

A
Anonymous
about 1 month ago
Read
Explore All Articles