Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

MPUG

Cathy from Bismarck, ND asks: I have a resource that has done some of the work on a task and they will be leaving the project.  How do I assign another resource to the task and have the new resource complete the remaining work?

Answer:  There are actually two ways to accomplish this — the regular way and the lazy person’s way. In both examples I’ll assume that the replacement resource has been added to the resource sheet.

Here’s the situation that needs altering. Note in Figure 1 that the resource has performed four hours of work on a 16-hour task and has 12 remaining hours of work.

Figure 1. Here’s the resource that needs replacing.

Ask the Teacher: Substituting Resources, Plus Changing the Current Date

1. Select the task in the Gantt chart and split the screen (Windows | Split).
2. Right click in the bottom pane and select Resource Work.
3. Select the resource name in the name field under the list of assigned resources.
4. Note the amount of remaining work on the current resource.
5. Replace the remaining work with a zero.
6. Enter the remaining work value in the remaining work for the replacing resource.
7. Click OK.

Another (lazy!) way of doing this is:

1. In the Gantt chart view, click on the task where you’d like to replace the resource, click on the Assign Resource icon, or click Alt-F10.
2. Click on the resource name to be replaced.
3. Click on the replace button.
4. Click on the new resource.
5. Click OK.
6. Click Close to close the form.

Figure 2 is an example that shows the result of performing the above steps to replace the resource. If you split the screen and look at the detail on the task, the remaining work will be moved to the replacement resource.

Figure 2. Whether you go the lazy route or not, the results are the same.

Ask the Teacher: Substituting Resources, Plus Changing the Current Date

Note: The baseline work value will stay with the original resource in both cases.

Bonus Question! Chris from Raleigh, NC asks: I want to change the current date of the project to use for forecasting the project schedule. Currently, I’m changing the system’s date before starting Microsoft Project. Is there an easier way of doing this?

Answer: Try Project | Project Information and change the current date on the right side of the form. This will change the date for just this project and won’t affect other programs or files.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Ask the Teacher: Substituting Resources, Plus Changing the Current Date

Cathy from Bismarck, ND asks: I have a resource that has done some of the work on a task and they will be leaving the project.  How do I assign […]

2 min read
•over 17 years ago••
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help
Articles
5 min read

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help

Microsoft Project Online retires September 2026. Learn why now is the time to plan your transition to modern portfolio management and join our free webinar on January 28.

T
The MPUG Community
2 days ago
Read
Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
2 months ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
2 months ago
Read
Explore All Articles