By default, the lag set between tasks is displayed in the Predecessor column of the Gantt chart view. Neither Microsoft Project 2007 nor Project 2010 has a separate field to display the lead or lag of specific tasks.

You can display the lag as a separate field by following these steps:

  1. In Project 2007 choose Tools, Customize Fields. In Project 2010 choose Project ribbon | Custom Fields in the Properties group.
  2. In the Custom Fields dialog, select the Task radio button. Then choose the Type drop down and select Text.
  3. Select Text1 and click the Rename button. Change the name to “Lag” and choose OK. This will display “Lag (Text1).”
  4. Click the Formula button of Custom attributes, enter the following formula, and click OK:IIf(InStr([Predecessors],”+”)<>0, Mid([Predecessors],InStr([Predecessors],”+”),Len([Predecessors])), “”)You’ll get a warning message that existing data in the Lag field will be deleted because now all values will be calculated by the formula. Click OK.
  5. Insert a column with the Field name as Lag (Text1) in Project 2007 by choosing Insert | Column. In the Field name dropdown, choose Lag (Text1). In Project 2010, just right-click on the column next to which you want the new column added and choose Insert Column. Scroll down to Lag (Text1) and select it.

How To Display Lag between Tasks in Your Gantt Chart

You may be wondering about that formula I’ve asked you to enter. What does the code mean?

For the purposes of illustration, let’s say the lag between Prepare and Review tasks is 1FS+2days (translated to: “The task is planned to Start with a lag time of two days after the Finish of its predecessor task”).

The part of the code that specifies:

InStr([Predecessors],”+”)

returns the position of + in the [Predecessors] field. That’s four in the example shown in the screenshot.

This code:

Mid([Predecessors],InStr([Predecessors],”+”),Len([Predecessors]))

extracts the text from + to the end of the string, which is “+2days.”

If you want display the lag to the right or left of the task bar, follow these steps:

  1. In Project 2007 choose Format | Bar Styles. In Project 2010, choose Format ribbon | Bar Styles in the Bar Styles group.
  2. Select the rows in the top area that you want the lag displayed next to.
  3. Select the Text tab in the bottom and choose the dropdown for Left or Right.
  4. Select the field name Lag (Text1) and press OK.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

How To Display Lag between Tasks in Your Gantt Chart

By default, the lag set between tasks is displayed in the Predecessor column of the Gantt chart view. Neither Microsoft Project 2007 nor Project 2010 has a separate field to […]

2 min read
•over 15 years ago•Updated 10 months ago•
S
Sai PrasadAuthor
Project Management
Microsoft Project
Best Practices
Productivity
S
Sai Prasad

Content Writer

B Sai Prasad, PMP®, PMI-SP®, MVP Project, Senior Manager - Learning & Development, has been with service provider Cognizant Technology Solutions India Pvt. Ltd since 2001 where he was named winner of the company's Global Trainer of the Year award. He has spent 13,000-plus hours in mentoring, coaching, training 9000-plus practitioners on project management topics ranging from project management concepts, project risk management, project scheduling, Microsoft Office Project® to software estimation techniques. He is a Champion of Project Management from PMI India and also Associate Champion Advisory Committee, PMI India. He is awarded the Champion of the Quarter (Q4 – 2012) and Delivery Excellence Award (2011-2012, 2012-2013) from PMI India. He's also the editor of the project management book, Forecast Scheduling with Project 2010. He is a Microsoft Certified Technology Specialist (MCTS) in Project 2010.

View all articles by Sai Prasad
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
2 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
14 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles