When you have a summary of tasks where some tasks are ahead of schedule and others are behind, it’s hard to tell if you’re ahead or behind overall. This is simply because summary tasks in Microsoft Project don’t show progress by default. However, it’s very easy to fix by following the steps below:

  1. Place your cursor in a single cell anywhere on the left pane of the Gantt chart view.
  2. Right-click in the right pane and select Bar Styles.
  3. Press the Insert Row button.
  4. Type Summary Progress for the Task Name.
  5. On the Bars tab change the Shape to the bottom half selection (the fourth one down), change the Pattern to solid (the second one down), and change the Color to red.
  6. Select Summary in the Show For… Task field.
  7. Select Actual Start for the From field.
  8. Select Complete Through for the To field.
  9. Press OK

How to Show Progress on a Summary Task
Now you can match up the progress summary to the Current Date line.
How to Show Progress on a Summary Task

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

How to Show Progress on a Summary Task

When you have a summary of tasks where some tasks are ahead of schedule and others are behind, it’s hard to tell if you’re ahead or behind overall. This is […]

1 min read
•almost 18 years ago•Updated 15 days ago•
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

How Reserves Keep Projects Alive
Articles
4 min read

How Reserves Keep Projects Alive

Learn how project reserves protect your budget and schedule from unexpected risks, including when and how to use contingency, management, schedule, and cost reserves effectively.

R
Ronald B. Smith, MBA, PMP
12 days ago
Read
Why Platform Migrations Fail (And How to Land Yours Successfully)
Articles
4 min read

Why Platform Migrations Fail (And How to Land Yours Successfully)

Learn why platform migrations fail and how to land yours successfully using proven change management tactics for PMOs facing tool transitions like Project Online’s retirement.

T
The MPUG Community
15 days ago
Read
Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help
Articles
5 min read

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help

Microsoft Project Online retires September 2026. Learn why now is the time to plan your transition to modern portfolio management and join our free webinar on January 28.

T
The MPUG Community
25 days ago
Explore All Articles
Read