Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG

If you studied to take your Project Management Professional (PMP)® exam using A Guide to the Project Management Body of Knowledge (PMBOK® Guide) fourth edition and had to reschedule your exam date to on/after July 31, 2013, then you now have to take the PMP® Exam based on the new PMBOK® Guide fifth edition. The Project Management Institute (PMI)® will not make any exceptions to this rule.

There are notable changes between version four and version five of the PMBOK® Guide. For instance, the number of Knowledge Areas has been increased from 9 to 10 and the number of processes has been increased from 42 to 47. Although this change is simple if you look at it numerically, it is much more complex under the hood. Here’s an example:

The new Knowledge Area, called Project Stakeholder Management, was added to emphasize the importance of good stakeholder management on all projects. It contains four processes. Two of these processes were renamed and moved here from Project Communications Management. Two are new processes. That leaves three new processes that were added in other Knowledge Areas throughout the guide. In addition, many more processes were renamed.

Appendix X1 in the PMBOK® Guide fifth edition describes the bulk of the changes. A number of authors have also described these changes and made their analysis available on the web. A quick search for “PMBOK® 5 changes” will find them. It is, however, important to note that these articles don’t list all the detailed changes. For instance, the inputs, tools & techniques and outputs of almost every single process have changed. Some ITTOs have been removed and new ones have been added. You will therefore not find a complete description of all the changes.

Because of this large amount of changes throughout the PMBOK® Guide, it is impossible to simply “study the difference”. The changes are sometimes conceptual, sometimes dramatic and sometimes minor. But they are here and your PMP® Exam may require you to know them. “Upgrading” your knowledge from the fourth to the fifth edition can therefore not be done “change-by-change”. You have to apply a holistic approach.

However, it must also be said that just because the PMBOK® Guide has changed, project management itself hasn’t. The fundamental way in which projects are managed is still the same. The PMBOK® Guide is simply our general framework describing the activities & techniques that are commonly accepted to be good practices on most projects. In addition, just because the Project Cost Management Knowledge Area has changed from three to four processes doesn’t mean that Earned Value systems need to be changed as well.

In order to pass your PMP® exam you will need to be aware of the new definitions in the PMBOK® Guide. Studying them takes effort, dedication and time. Here is a possible study approach to “upgrade” yourself to the PMBOK® Guide fifth edition:

  1. Study Appendix X1 and familiarize yourself with the changes. In particular: Familiarize yourself with the processes that have been added, moved or renamed and learn the new process names.
  2. Study Appendix X3 and familiarize yourself with the Interpersonal Skills a project manager should have.
  3. Study Annex A1 – The Standard for Project Management of a Project. Here you want to Study the short descriptions for each of the five process groups and for each of the 47 processes.
  4. Study table 3-1 on page 61 and know which process belongs to which process group. (You will find that it contains the same information as Table A1-1 in Annex A1). For the exam it is a good idea to be able to start with a blank piece of paper and draw this table from memory.
  5. Study table 4-1 on page 78 and know which documents are part of the project management plan and which ones are “just” other project documents.
  6. And finally (and unfortunately): Study the complete PMBOK® Guide 5th edition twice.

When studying the new PMBOK® Guide familiarize yourself with the new inputs, tools & techniques and outputs of all the processes. A good approach is to study the Data Flow Diagram for each of the 47 processes. These diagrams illustrate the flow of the inputs and outputs and will strengthen your understanding of how they move between the many processes. It will also help you understand the integrated nature of all the processes in the PMBOK® Guide.

You should also get to know the new processes that have been added and make special note of the new Earned Value Calculations Summary Table 7-1 on page 224, which looks suspiciously close to a table that I developed and have published since 2009 for our PMP® Exam Formula Guide…

As you might have guessed by now, “upgrading” your knowledge to this new version of the PMBOK® Guide is not something that you can do in just a day. While your PM experience is the main focus of the PMP® Exam, it will also be necessary for you to have an in-depth understanding of the PMBOK® Guide fifth Edition to be able to correctly answer many of the questions the test.

I therefore recommend that you plan a minimum of two weeks of intense study.

PMBOK an is a registered mark of the Project Management Institute, Inc

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

How To Upgrade Yourself To The PMBOK® Guide 5th Edition

If you studied to take your Project Management Professional (PMP)® exam using A Guide to the Project Management Body of Knowledge (PMBOK® Guide) fourth edition and had to reschedule your […]

4 min read
•about 13 years ago•Updated 9 months ago•
C
Cornelius FichtnerAuthor
Project Management
Microsoft Project
Best Practices
Productivity
C
Cornelius Fichtner

Content Writer

Cornelius Fichtner, PMP is a noted PMP expert. He has helped over 47,000 students prepare for the PMP Exam with The Project Management PrepCast and The PM Exam Simulator.

View all articles by Cornelius Fichtner
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
12 days ago
Read
Context Engineering for Project Managers: Give AI the Project, Not Just the Question
Articles
1 min read

Context Engineering for Project Managers: Give AI the Project, Not Just the Question

Learn how to choose, date, and source the project information you give AI, so its risk analyses, status reports, and change request reviews reflect your actual project.

A
Anonymous
21 days ago
Read
The Climbing Rope – Why Projects Rise or Fall Together
Articles
1 min read

The Climbing Rope – Why Projects Rise or Fall Together

Ronald B. Smith uses a climbing rope to show how project team dynamics like trust, communication, and shared accountability decide who reaches the summit.

A
Anonymous
about 1 month ago
Read
Explore All Articles