Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

MPUG - Master Project User GroupMPUG - Master Project User Group

Rick from San Jose, CA asks: During the execution of my project, my baseline needs to be updated because of change requests from my clients. What is the best way to do this in Microsoft Project?

Answer: When the baseline of the project is set, it is set for all three areas of the data structure. Values will be set for tasks, assignments, and resources. There are technically 11 sets of baseline fields in the system, Baseline and Baselines 1-10. The Baseline field is the default used when you first set a baseline. When a baseline is updated, you select one of the other 10 sets of Baseline fields.

By default the Baseline fields will be used in the project variance calculations. Baseline fields 1-10 are used for earned value, updated baselines, or as free use fields for schedulers. If updated baselines are updated to use fields Baseline 1-10, the option to indicate an alternate baseline used for variance calculations should be set.

When setting a baseline, the fields in the first column of Table 1 will be copied and held in the fields in column two. The “estimated” fields are used for manually scheduled tasks in Project 2010:

Ask the Experts: Updating the Baseline
Set the baseline to the Baseline1 fields.If changes to the project schedule are approved and the customer agrees on the setting of a new baseline, follow the steps below. In the example, the baseline will be saved into the Baseline1 fields. Baselines 1-10 are available for this purpose:

2. Change the option to indicate which baseline should be used for the variance calculation.
3. Change a Gantt Chart View to display Baseline1 fields.
4. Change the Variance tables to view the Baseline1 fields.

Step 1

To set the baseline to the Baseline1 fields in Project 2010:

1. Project | Set Baseline | Set Baseline.
2. Set Baseline — Baseline 1.
3. For Entire Project.
4. Click OK.

To set the baseline to the Baseline1 fields in earlier Project versions:

1. Tools | Tracking | Set (or Save) Baseline.
2. Set Baseline — Baseline 1.
3. For: Entire Project.
4. Click OK

Step 2

To change the option to indicate which baseline should be used for the variance calculation in Project 2010:

1. File | Options | Advanced | Earned Value option for this project.
2. Select Baseline 1.
3. Click OK to close the box.

Ask the Experts: Updating the Baseline

To change the option to indicate which baseline should be used for the variance calculation in earlier Project versions:

1. Tools | Options | Calculations | Earned Value.
2. Click on the Baseline for Earned Value calculations and select Baseline1.
3. Click Close.

Ask the Experts: Updating the Baseline

Step 3

To change a Gantt Chart View to display Baseline1 fields in Project 2010:

1. Display a Gantt Chart View.
2. Format | Baseline | Baseline1.

Ask the Experts: Updating the Baseline

To change a Gantt Chart View to display Baseline1 fields in earlier Project versions, select a view to copy. It will be easier if you select one that already is using displaying the baseline. In the example below, a copy of the Tracking Gantt view will be changed:

1. Best Practice — copy the Tracking Gantt and change the copy.
2. View | More Views | Tracking Gantt | Copy.
3. Rename the view “Tracking Gantt using Baseline1.”
4. Click Show in the Menu.
5. Click OK.
6. Click Apply

To change the formating to see the Baseline1 fields:

1. Format | Bar styles.
2. Change the From and To columns for the Baseline fields to Baseline1 Start and Baseline1 Finish. (See the figure below.) Scroll down and change the values of the rollup baseline fields if using rolled up task bars.
3. Click OK to close the box.

Ask the Experts: Updating the Baseline

Step 4

Change the Variance tables to view the Baseline1 fields works the same in all versions of Project.

1. Right click in the upper left corner above the ID numbers and select Variance.

Ask the Experts: Updating the Baseline

2. Double click on the column heading Baseline Start.
3. Select Field Name Baseline1 Start.
4. Click OK if you’re using a version earlier than Project 2010.
5. Double click on the column heading Baseline Finish.
6. Select Field Name Baseline1 Finish.
7. Click OK if you’re using a version earlier than Project 2010.

The Variance Table and Gantt Chart View using the Baseline field values are displayed in the figure below. Baseline Start and Baseline Finish display for Baseline values. Note the values in the Variance columns:

Ask the Experts: Updating the Baseline

Changes in the schedule were made and the baseline was set using the Baseline1 fields. The Variance Table and Gantt Chart View displaying the Baseline1 field values are shown below. Note the changes to the Start and Finish Variances and Gantt bars. Baseline1 Start and Baseline1 Finish are used to display the baseline dates. Note the values in the Variance columns.

Ask the Experts: Updating the Baseline

Each baseline is dated by the date the baseline was set to keep a history of the baselines used during the execution of a project. It’s also advantageous to create Gantt Views that display multiple baselines for comparison. The Multiple Baseline Gantt view is preset to display Baseline, Baseline1, and Baseline2 for this purpose.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

Ask the Experts: Updating the Baseline

Rick from San Jose, CA asks: During the execution of my project, my baseline needs to be updated because of change requests from my clients. What is the best way […]

4 min read
•over 15 years ago•Updated 22 days ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

How Reserves Keep Projects Alive
Articles
1 min read

How Reserves Keep Projects Alive

Learn how project reserves protect your budget and schedule from unexpected risks, including when and how to use contingency, management, schedule, and cost reserves effectively.

A
Anonymous
19 days ago
Read
Why Platform Migrations Fail (And How to Land Yours Successfully)
Articles
1 min read

Why Platform Migrations Fail (And How to Land Yours Successfully)

Learn why platform migrations fail and how to land yours successfully using proven change management tactics for PMOs facing tool transitions like Project Online’s retirement.

A
Anonymous
21 days ago
Read
Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help
Articles
1 min read

Beyond Project Online: Why Now Is the Time to Plan Your Move to Modern Portfolio Management and How We Can Help

Microsoft Project Online retires September 2026. Learn why now is the time to plan your transition to modern portfolio management and join our free webinar on January 28.

A
Anonymous
about 1 month ago
Read
Explore All Articles