Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG

Barbara from Denver, CO asks: I want to used earned value calculations to help manage my projects. However, when I look at the BCWS and BCWP fields, the data doesn’t seem to be calculated. What’s going on?

Answer: Earned value can be a very helpful indicator of the health of your project. It’s the equalizer between duration and work in evaluating project performance. For instance, did you do the work you planned to perform in the timeframe you planned to perform it? Did the work cost you more (more time) than you planned and how does that relate to the schedule?. Earned Value is complicated and can’t be addressed fully in this article. However, I would like to address the question above.

Earned value calculations need several values to be able to calculate. If something’s missing or awry, the earned value function won’t work.

  • If you’re not using costs (a value in the standard cost field on the Resource Sheet), earned value won’t calculate. Most of the Microsoft Project earned value calcuations are using the cost values calculated per task.
  • The accuracy of assignments on tasks will influence the accuracy of calculations (correct number of hours = correct costs).
  • If resource calculators aren’t up to date, resource assigments won’t be accurate because resources are scheduled based on availability.
  • Most of the earned value calculations also are looking for initial schedule values. This means if you don’t have a baseline set, you won’t see earned value.
  • Earned value will also be calculated based on a specific status in time. Therefore, the status date must be set or earned value won’t calculate.
  • Track the project — actuals must be entered.
  • Uncompleted work has to be rescheduled in order to keep the schedule accurate for the future calculations.

In the earned value table below I set the baseline for this short project. Go to View | Table | More Tables | Earned Value.

Figure 1. A sample project to demonstrate earned value.

Ask the Teacher: Earned Value Doesn’t Want to Calculate

For this example, the project started on September. 1, 2008. Note that there are only values in EAC (Estimate at Completion) and BAC (Budget at Completion), which is actually the baseline cost. Also note that the values are matching at this time. When I pointed to the EV (earned value) field, the option popped up to get help for a field. This is a wonderful place to see in detail how a field is actually being calculated. I also encourage you to see the calculations for each of the fields so you understand how they work before you start to depend on them for project forecasting.

Now I’ll enter some actual values as work performed on tasks. Tasks 3 and 4 are marked completed later than scheduled. Task 5 is 50% complete. The remaining work was increased by three days also. After the tracking information was entered, there was no change to the EV table. I then entered a status date of September 14, 2008 at Project | Project Information | Status Date | OK. Figure 2 shows the result.

Figure 2. The sample project showing updated values after modifying the status date.

Ask the Teacher: Earned Value Doesn’t Want to Calculate

As you can see, values have been updated in all of the fields.

There are also two other standard EV tables called Earned Value Schedule Indicators and Earned Value Cost Indicators. There’s an option to use physical percent complete (Tools | Options | Calculations | Earned Value) for these calculations instead of the default of duration percent complete. In this same dialog for options you can also select an alternate baseline to be used for the EV calculation. The physical percent complete would allow you to post a percentage instead of using the pre-calculated percentage. Physical Percent complete is available on the Tracking table or may be inserted into any table as needed.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Ask the Teacher: Earned Value Doesn’t Want to Calculate

Barbara from Denver, CO asks: I want to used earned value calculations to help manage my projects. However, when I look at the BCWS and BCWP fields, the data doesn’t […]

3 min read
•about 18 years ago•Updated 10 months ago•
E
Ellen LehnertAuthor
Project Management
Microsoft Project
Best Practices
Productivity
E
Ellen Lehnert

Content Writer

Ellen Lehnert, PMP, Microsoft Project MVP, MCP, is a independent consultant and trainer on Microsoft Project and Project Server. She has taught Microsoft Project over 400 times and is the author of  MS Project 2010 and 2013 published courseware. Ellen is also a contributor and tech editor for many reference books, a developer for the Microsoft Project certification tests and is a frequent meeting speaker for Microsoft, MPUG and PMI. Contact Ellen at ellen@lehnertcs.com.

View all articles by Ellen Lehnert
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
11 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
30 days ago
Read
Context Engineering for Project Managers: Give AI the Project, Not Just the Question
Articles
1 min read

Context Engineering for Project Managers: Give AI the Project, Not Just the Question

Learn how to choose, date, and source the project information you give AI, so its risk analyses, status reports, and change request reviews reflect your actual project.

A
Anonymous
about 1 month ago
Read
Explore All Articles