Back to ArticlesBack

Join 500,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

MPUG

Project for the Web was first released in 2019. Since then, Microsoft has continued to add new content to this lightweight project management application on a regular basis. In fact, feel free to take a look at the blog post with a video that I created back in November 2020 about the new Export to Excel feature in Project for the Web.

Microsoft has recently announced the new Export Timeline to PDF feature that will assist users with project reporting. To access this new feature, complete the following steps:

1. Navigate to Home page of your organization’s Project for the Web.

2. Click the name of a project to open it for editing.

3. Click the Timeline link at the top of the page to apply the Timeline view to your project, such as shown in Figure 1.

Figure 1: Apply the Timeline view

4. For best results, click the Zoom slider at the top of the page and set the level of zoom to either the 2-Weeks level or the Monthly For example, notice in Figure 2 that I set the zoom to the 2-Weeks level. Completing this step will generate a more useful PDF document in the export process.

Figure 2: Click the Zoom slider

5. In the upper right corner of the page, click the More actions button (the … button) and select the Export Timeline to PDF item, such as shown in Figure 3.

Figure 3: Select the Export to PDF item

The system begins the process of creating the PDF document, and when completed it displays a button for the new PDF document at the left end of the Status bar, such as shown in Figure 4.

Figure 4: Link for the PDF document

6. In the newly-created PDF button, click the pick list arrow button (the ^ button) and select the Open item on the popup menu, such as shown in Figure 5.

Figure 5: Click the Open button

The system opens the PDF document in your web browser, such as shown in Figure 6. The system saves the exported PDF document using the same name as the project, and displays in the project name in the upper left corner of the document. The exported PDF document displays the Name, Assigned to, Start, Finish, and % Complete columns on the left side of the page, along with the timeline of the project on the right side of the page.

Figure 6: Exported PDF document

Warning: For best results with the export process, I strongly recommend that you set the level of zoom so that you can view the entire project schedule without scrolling right and left. If this is not possible, you may find that the resulting PDF document is practically unusable because of how the export process breaks the Timeline view into multiple pages in the PDF document.

Get Weekly PM Insights

Join 500,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemap
Articles

How to Export to a PDF Document in Project for the Web

Project for the Web was first released in 2019. Since then, Microsoft has continued to add new content to this lightweight project management application on a regular basis. In fact, […]

3 min read
•over 4 years ago••
D
Dale HowardAuthor
Project Management
Microsoft Project
Best Practices
Productivity
D
Dale Howard

Content Writer

Dale Howard is currently a Senior PPM Consultant with Arch Systems, Inc. His hair and beard have turned white because of using Microsoft's project management tools for more than 20 years. Dale started his career using Microsoft Project 4.0 for Windows 95 and began using Microsoft's PPM tools when they introduced Project Central in 2000. Dale is the co-author of 23 books in Microsoft Project, Project Server, and Project Online. He is currently one 0f 26 Microsoft Project MVPs in the entire world and one of only 4 Project MVPs in the United states.

View all articles by Dale Howard
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Two Project Manager Agent Features You Might Like
Articles
5 min read

Two Project Manager Agent Features You Might Like

Discover two game-changing features of Microsoft’s Project Manager Agent including agent-to-agent communication and the new integrated interface in Planner.

E
Erik van Hurck
about 2 months ago
Read
Master Dependency Analysis in Microsoft Project with SSI Tools!
Articles
2 min read

Master Dependency Analysis in Microsoft Project with SSI Tools!

Learn how to master dependency analysis in Microsoft Project using SSI Tools’ Directional Path, Connecting Path, and Dependency Tracer to analyze predecessors, successors, and project logic.

K
Kenny Arnold
about 2 months ago
Read
A PM’s Halloween Survival Guide
Articles
5 min read

A PM’s Halloween Survival Guide

Discover the spooky parallels between Halloween and project management, from scope creep monsters to ghosted team members, in this fun survival guide for PMs.

R
Ronald B. Smith, MBA, PMP
2 months ago
Read
Explore All Articles