Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG - Master Project User Group

Mid-point or block scheduling involves a sequence of tasks, the scheduling of which is dependent upon the start of a target task embedded within the sequence. In practice, as the sequence is moved forward or backward within the schedule, start-to-finish (SF) task relationships are used to drag the predecessors of the target task along with the target task. Here is an example.

Figure 1. Example of mid-point or block scheduling with SF relationships.

The start of the target task, “Move to new office,” depends upon the completion of the preparation task. If preparation completion is delayed, the entire move sequence is delayed.

Figure 2. Example with start of target task delayed.

If preparation completion is accelerated, the start of the sequence is accelerated. In this case, it is accelerated to a date before the start of the project. Project issues a warning. We would need to compress the predecessor tasks in order to take advantage of the accelerated move date.

Figure 3. Example with start of target task accelerated, along with a warning.

However, if we baseline and track the schedule, it does not behave as we might expect. Let’s assume that by the end of the fourth time period, the preparation task is completed as expected, but the box distribution task did not start on time.  Project’s calculations are correct. Having more than zero days of lag between the start of the packing task and the finish of the distribution task does not invalidate the SF relationship. As a consequence, the move task is not delayed.

Figure 4. Baselined example with tracking.

What’s Wrong?

There are several issues regarding the use of SF relationships in the example.

First, while Project computed float correctly relative to using SF relationships, the float calculations are counter-intuitive. If the box distribution or packing tasks are delayed, the move task should be delayed. However, the schedule indicates that these preceding tasks have float. See Figures 1-3.

Second, schedule perturbations may cause the tasks with SF relationships to track in a counter-intuitive manner, as shown in Figure 4.

And lastly, in general, the DCMA scheduling guideline admonishes against the use of SF relationships (see paragraph 4.4), negative lag (see paragraph 4.2), and unbound tasks (see paragraph 4.1).  The arithmetic equivalents of the SF relationships used in this example are finish-to-start (FS) relationships with negative lag. Further, the start of the first task in the sequence is unbound. While the finish of the box distribution task is preceded by the start of the packing task, the start of the distribution task does not have a predecessor.

Even with these issues, it is difficult to dissuade a scheduler from using SF relationships in mid-point scheduling. After all, the dates and behavior of the initial schedule appear to be correct.

An Alternative

Here is an alternative that does not use SF relationships. The sequence is clearly defined as a series of FS relationships. The start of the sequence is linked to the start of the project. The two predecessor tasks in the sequence are scheduled as late as possible using the tasks’ late start and finish times. This corrects the float calculations and shows the two predecessors as being critical.

Figure 5. An alternative.

If preparation completion is delayed, the sequence is delayed accordingly.

Figure 6. Alternative with delayed move availability date.

If the preparation completion is accelerated, the sequence is not scheduled before the beginning of the project. In this case, it is the combined length of the predecessors in the sequence, not the finish of the preparation task, that drives the move date. This forces us to recognize that one or both of the predecessor tasks must be compressed in order to accelerate the move date. The preparation task is no longer critical.

Figure 7. Alternative with accelerated move availability date.

Tracking with the alternative clearly shows that a delay in starting the box distribution task will delay the start of the move.

Figure 8. Baselined alternative with tracking.

What do you think?

Have you seen or used mid-point scheduling in practice?  Would you prefer using the alternative?  Please share your thoughts in the comments below.

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM Glossary

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUG Logo

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Removing Start-to-Finish Relationships from Mid-point Scheduling

Mid-point or block scheduling involves a sequence of tasks, the scheduling of which is dependent upon the start of a target task embedded within the sequence. In practice, as the […]

4 min read
•over 6 years ago•Updated 3 months ago•
R
Robin NicklasAuthor
Project Management
Microsoft Project
Best Practices
Productivity
R
Robin Nicklas

Content Writer

Robin Nicklas is a project management consultant and educator. Since 2001, he has trained project managers in the aerospace, financial, telecommunications, government, and software sectors. Prior to teaching, he spent twenty years in information systems and technology, twelve of which he managed software development at large information service companies. Since 2003, he has taught graduate and undergraduate courses in project management at the University of Washington in Seattle, as well as MS Project courses at Bellevue College Continuing Education since 2011. Robin is a former president of the PMI Puget Sound Chapter in Seattle and a certified PMP. He can be contacted through his website, robinnicklas.com.

View all articles by Robin Nicklas
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

The Integrated Master Plan: Terrible Name, but a Great Idea
Articles
1 min read

The Integrated Master Plan: Terrible Name, but a Great Idea

The Integrated Master Plan uses events, accomplishments, and criteria to define objective progress before scheduling begins. Here’s what it is and why it works.

A
Anonymous
10 days ago
Read
Managing the Sands of Time: How IT Projects Reflect an Hourglass
Articles
1 min read

Managing the Sands of Time: How IT Projects Reflect an Hourglass

Discover how the hourglass metaphor reveals the way time, tasks, and momentum work together in IT project management — and why managing the flow is the key to project success.

A
Anonymous
17 days ago
Read
Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown
Articles
1 min read

Your Project Online Migration Questions, Answered: Key Takeaways from Ira Brown

Ira Brown, president of Project Widgets, breaks down the four realistic migration paths, key deadlines, and a pre-migration inventory checklist to help your organization plan ahead of the September 2026 Project Online retirement.

A
Anonymous
about 1 month ago
Read
Explore All Articles