Reply To: Formatting of “Notes” field in views

Home Forums Microsoft Project Discussion Forum Formatting of “Notes” field in views Reply To: Formatting of “Notes” field in views

#6661
Avatar photoCommunity
Keymaster

Hi Martin,

It has ever been thus. The Notes field is limited to 256 characters or a return character whence you will then see the ellipsis … indicating there is more text.  Double clicking on this task will open Task Information and then Notes field for your additional information.  I can’t see Microsoft ever changing this as the Tables which hold the Notes would become extremely unwieldy.

However, why don’t you list all the legitimate tasks in the normal way, indent them and then close them down so that only the Summary Task is shown?

FAQs, companion products and other useful Project information can be seen at this web address:  http://project.mvps.org/faqs.htm

Hope this helps – please let us know how you get on 🙂

Mike Glen
MS Project MVP