Laurel,
My guess is that these were setup as Generic “Resources”, than Generic “Users”. If that is correct, then you will find them in “Resource Center”.
if they were set up as Generic Users, for some reason, then you will need to go to Resource Center, confirm they are not Generic, and then make sure the option box “resource can log on to Project Server” is checked.