Reply To: Handling multiple country holiday schedules

Home Forums Microsoft Project Discussion Forum Handling multiple country holiday schedules Reply To: Handling multiple country holiday schedules

#7012
Avatar photoCommunity
Keymaster

I agree with Ben. If you still need to manage holidays on an individual level than you can treat holidays as you would any other PTO. Start with a generic standard calendar without holidays and enter holidays per person depending on where they will be. That of course assumes that you have a good forward schedule of when each of your team members will be in which country. If that’s not the case, then Ben’s suggestion is that much more preferred.