Reply To: I’m looking for a way to see the resource levels that can be added in the resource information general tab by period all at once.

Home Forums Discussion I’m looking for a way to see the resource levels that can be added in the resource information general tab by period all at once. Reply To: I’m looking for a way to see the resource levels that can be added in the resource information general tab by period all at once.

#10500
Community
Keymaster

And to make this even slicker, you can add a field for grouping – maybe skill. Then when you apply grouping on this field to the Resource Usage view, you get the total for Work, Remaining Availability, etc. for the group.

Graham