Reply To: Problem Modifying Row Height in Tracking Gantt view table

Home Forums Microsoft Project Discussion Forum Problem Modifying Row Height in Tracking Gantt view table Reply To: Problem Modifying Row Height in Tracking Gantt view table

#6291
Avatar photoCommunity
Keymaster
Regina, I have found that the bar type text, when added to the top or bottom of the bar, causes the overall row height to expand. I think you have a number of text fields selected to be placed on the top of the bar.