Reply To: Recommendation – Using ‘PERT Chart Expert’ software

Home Forums Discussion Recommendation – Using ‘PERT Chart Expert’ software Reply To: Recommendation – Using ‘PERT Chart Expert’ software

#10509
Avatar photoCommunity
Keymaster

I have used the PERT capabilities on projects I have had in the past.  However, my current company uses MS Project Server extensively to not only schedule our efforts but to manage a large pool of team members.  Our efforts are highly creative in nature (web development), and largely effort-based, rather than duration based.  It has been my experience that the PERT functionality only works with duration.  I am playing around with methods to translate those entries into a PERT entry, but I would really love to have PERT in nmy schedule for effort instead of duration.  Has anyone one else done this?