I have used the PERT capabilities on projects I have had in the past. However, my current company uses MS Project Server extensively to not only schedule our efforts but to manage a large pool of team members. Our efforts are highly creative in nature (web development), and largely effort-based, rather than duration based. It has been my experience that the PERT functionality only works with duration. I am playing around with methods to translate those entries into a PERT entry, but I would really love to have PERT in nmy schedule for effort instead of duration. Has anyone one else done this?