Reply To: Subplanning within masterplan gives wrong end-date

Home Forums Discussion Subplanning within masterplan gives wrong end-date Reply To: Subplanning within masterplan gives wrong end-date

#6081
Avatar photoCommunity
Keymaster
Make certain the calendars match in the projects. If the master uses a standard (default) calendar and so do the subprojects, then also verify the standard calendar has not been modified in the subproject files.
A common error is to modify the standard calendar with company holidays, etc.
-Jim Aksel