Reply To: WBS Renumbering not working with MS Project 2010

Home Forums Discussion WBS Renumbering not working with MS Project 2010 Reply To: WBS Renumbering not working with MS Project 2010

#6641
Community
Keymaster

Did you have a customized defined WBS code in the file that you used to convert to 2010?  If you did, check to make sure that you still have the defined code:  Project –> WBS –> define code.  If the code defination is missing, add it back in.  Then go to Project –> WBS –> Renumber and select to renumber the project or a selected group of tasks.  The renumber is activated when a at least 1 line is defined for the code define for the WBS.

Hope this helps.

Ellen Lehnert, MVP