Reply To: What is with the print view horizontal lines?

Home Forums Discussion What is with the print view horizontal lines? Reply To: What is with the print view horizontal lines?

#6431
Community
Keymaster

Hi,

It sound as if you have Updated Project to the Status Date, thus moving uncompleted tasks or parts of tasks to start at the Status Date.  The lines you are referring to show how much the tasks have been moved.

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials