Reply To: Why the total days are in correct in summary task ?

Home Forums Discussion Forum Why the total days are in correct in summary task ? Reply To: Why the total days are in correct in summary task ?

#6610

If you are using manual mode the totals will not necessarily add up to the total duration.  If the tasks are in automatic and are linked FS they should add up to the total duration of each task on the summary.  However, customized fields have an option of rolling up and so do baselines.