Tagged: Microsoft Project Server 2010
I am working in a Project Server 2010 environment, with about 50 different projects. Each project has a Project Lead with PWA ability to update their schedule. Many of these project schedules have baseline dates under Configuration Control Board control. It is essential that any tasks/milestones that are “baselined”, cannot be deleted. Does anyone know how to prohibit the deletion of these tasks. This a HUGE concern and we would be immensely grateful for a solution.
Thanks!
Tom Mc
Let me supplement my original questions with another question: Can any fields be blocked from editing? That is, we want certain people to be able to view field data, like Baseline dates, but not be able to change them.
Tom Mc
You could use the security functions within PWA to allow only certain data to be readable for that user but there is no way to lock fields in Microsoft Project.