Loading...
Quick Links

Project Server 2010 – Timesheets

Home Forums Discussion Project Server 2010 – Timesheets

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #2213 Reply
    Community
    Keymaster

    Has anyone configured timesheets to display only the project level information in the timesheet itself?  The resources are assigned to the project tasks like normal but I would like the timesheet to display only the project level for the specific interval & for time to be recorded at that level only.  Any insight into how this can be accomplished would be much appreciated! Gemma Bevilacqua

    #6659 Reply
    Community
    Keymaster

    Gemma, there is an option within Server Settings, Timesheet Settings and Defaults called Default Timesheet Creation Mode.  Setting that to Current Projects will prepopulate the timesheet with top level tasks.  These tasks do not sync back to the project plan.  If you are using 2010 than you also need to select the Allow Top Level Time Reporting option under Timesheet Policies further down the page.  Hope that helps.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Reply #6659 in Project Server 2010 – Timesheets
Your information: