Hi
I m working with MS Project 2016.
How can I see the total work cost and the total materials cost for each task and all Project?
Regards,
Carlos Santos
Sorry, not without exporting the data…or possibly using VBA.
Larry
Thank you very much for your answer.
In fact this weekend I did as you replied.
I export data to excel and I think I get something.
Regards,
Carlos