Back to ArticlesBack

Join 50,000+ PM Professionals

Get expert PM insights, PMP prep tips, and earn PDUs with exclusive content delivered weekly.

Protected by reCAPTCHA: Privacy & Terms

MPUG - Master Project User GroupMPUG

Project Managers are often eager to undertake additional challenges. Experience shows the seasoned manager under-commits and over-delivers as opposed to the alternative (over-committing and under-delivering). There are real world processes and tools in place that can help the Project Manager understand and make realistic commitments. Before commitments to accept extra work are communicated, there exists a recommended practice to understand and analyze the impact of a change to the work. AACE International, the Authority for Total Cost Management® has published recommended practice number 52R-06 which spells out the practice for taking on more work, a change, and reasonably communicating the impact. This analysis is performed rather easily using Microsoft Project.

Time Impact Analysis (TIA) is a scheduling technique used to assess and quantify the effects of an unplanned event, namely a change which increases the work scope, but can be used in other ways. A TIA can also be used to evaluate potential impacts to the schedule for acceleration or delay. A TIA is forward-looking. Requirements for performing a TIA stipulate that your schedule must have a valid critical path. The TIA is applied to the most recently updated and accepted critical path method (CPM) schedule. The TIA permits the team to examine and analyze the change of project completion between the original plan, the non-impacted schedule, and the impacted schedule with acceptance of additional work.

According to AACE International’s recommended practice No. 52R-06, there are eight steps for understanding scope change and the impact to a finish date. Those eight steps are:

1) Develop and approve schedule fragnet to model the extra work. Provide a CPM schedule of the additional changed work and get the schedule approved.

Although the TIA method can be used in any project, including information technology, facility construction, business acquisitions, maintenance, and production plant outages, this example is an engineering project related to the electrical transmission grid. The change from an existing originally planned Oil Cooled Breaker to a Gas Cooled Breaker in a substation is examined and the fragnet of the extra work is documented.

NOTE: The screenshots below are with Project 2013, but TIA can apply to all versions of Microsoft Project.

tia1

2) Obtain the most recently updated approved schedule. This supports and gives reason to routine updating of the schedule. An older schedule update should not be used, rather, use the approved schedule that most recently reflects where work status stands.

tia2

3) Set the durations of the extra work activities (fragnet) to zero. Merge the MS Project 2013 files of the current schedule and the fragnet to get the schedule below.

tia3

4) Insert the approved durations into your fragnet (schedule of new work) and recalculate the critical path.

tia4

5) Identify the activities used to measure the delay. Here is a special note: if your inserted fragnet does not show up on the critical path, it will not delay the project. However, there may still be a resource availability issue. Resource capacity and existing workload can also be checked, but that is a topic for another paper. In the case above, redesigning the work based on the change in specifications of a breaker causes a time impact to the remaining tasks.

6) Determine the correct time impact of delay. In the above example, the project is already delayed due to slow progress on task 7, and overall the project is beyond the baseline by 10 days. Changing the work further delays the critical path and the time impact analysis illustrates an additional 12 day delay to the projected finish date. Overall, the impact from additional work to the project finish is 12 days.

7) Determine the actual dates of the delay. This step is calculated and shown above. The yellow double arrow shows the delay due to the extra work.

8) Lastly, eliminate any delay that was already in the schedule (the difference between the finish date with the fragnet and the recently updated CPM schedule is the delay impact due to acceptance of the change / extra work).

That concludes using Microsoft Project to implement recommended practice 52R-06 as defined by AACE International.  This analysis can be used in all types of projects.  This schedule analysis and impact method does not determine cost impact to one’s schedule.  Performing a TIA helps PMs understand the impact of extra work, and gives PMs the tools to communicate impact to the project finish date.  The sooner the customer knows the impact of change, the more effective one is at managing and controlling the change.

MPUG You Logo

h3>Learn how an MPUG Membership helps individuals and teams become better project managers and Microsoft Project users through Microsoft Project Training.

Join MPUG to attend live training webinars, access 500+ hours of on-demand sessions, receive certificates of completion and earn the Project Management Institute (PMI)® Professional Development Units (PDUs) that you need.


Watch an MPUG training webinar for free and improve your Microsoft Project skills in less than 1 hour.


[ezcol_1third]

FREE MPUG Resources

  • Microsoft Project Tutorial
  • Tips from a Microsoft Project MVP
  • Webinar: Microsoft Project Do’s and Dont’s
  • The Project Communication Plan
  • Creating an Agile Schedule
  • 15 Tips for New Users
  • MPUG Newsletter
  • Want access to more? Join MPUG Today!

[/ezcol_1third]

[ezcol_1third]

Microsoft Project Resources

  • Microsoft Project User Group
  • Online Training
  • Microsoft’s Project Website
  • Try Microsoft Project for FREE!
  • Microsoft Project Certifications

[/ezcol_1third]

[ezcol_1third_end]

Additional Resources

  • Create a Monthly Cash Flow Report in Microsoft Project 2016
  • What is Project Management?

[/ezcol_1third_end]

Get Weekly PM Insights

Join 50,000+ PMs receiving updates on the latest PM methodologies, PDU opportunities, tool reviews, career tips, and member exclusives.

Protected by reCAPTCHA: Privacy & Terms

PMI ATP
PMI Authorized Training Partner
REP #4082

Learning Paths

PMP® TrainingCAPM® TrainingPgMP® TrainingPMI-ACP® TrainingMS ProjectMS PlannerMS TeamsJira

PM Resources

PDU TrackerLive WebinarsSalary CalculatorTool ComparisonsJob BoardKnowledge BasePM GlossaryOur Faculty

Community

Discussion ForumStudy GroupsEvents Calendar

Follow Us

LinkedInYouTubeTwitterFacebook
MPUGMaster Project User Group

© 2026 MPUG. All rights reserved.

TermsPrivacySitemapAdvertise
Articles

Time Impact Analysis: Extra Work and the Effect on the Finish Date

Project Managers are often eager to undertake additional challenges.  Experience shows the seasoned manager under-commits and over-delivers as opposed to the alternative (over-committing and under-delivering).  There are real world processes […]

5 min read
•over 12 years ago•Updated 10 months ago•
T
Tony Woodrich, PMP, CCP - Certified Cost ProfessionalAuthor
Project Management
Microsoft Project
Best Practices
Productivity
T
Tony Woodrich, PMP, CCP - Certified Cost Professional

Content Writer

Tony Woodrich has a Bachelor's of Science in Civil Engineering from the United States Air Force Academy and a MBA from Bentley University. Tony is a PMP, and Certified Cost Professional (from AACE International - The Association for the Advancement of Total Cost Management). Tony started his career at the Air Force's Electronics Systems Center purchasing R&D programs, notably, Tony was lead buyer/contract negotiator for early prototypes of IR cameras, and early electronic appliances that switched analog signal to digital fiber optic signals. Tony also worked in Civil Engineering as the Base Prime BEEF (Base Emergency Engineering Force) Chief. After an honorable discharge from the US Air Force as Captain, Tony joined Administrative Controls Management, supporting cost estimating, planning, scheduling and developing resource loaded CPM scheduling systems for Pharma projects, nuclear plant work, product development, and testing for an Automotive OEM, including certification emissions testing requirements, and powertrain operations engine engineering calibrations. Tony's team supported the FAA with an IDIQ contract recovering airway facilities after natural disasters, including recovering GUAM after Typhoon Paka. Using resource and cost loaded PM tools, Tony's team assisted an investor owned utility in successfully selling a transmission system, and assisted the buying company to establish itself with the regulators approval as the owner and steward of that multi-billion dollar asset, establishing capital project scheduling systems, and maintenance planning and scheduling systems. Templates developed by Tony's team were used to acquire and operate two additional investor owned utility's transmission systems. Tony's team helped an R&D Pharmaceutical company acquire a saleable drug product from a large European Pharma, as a revenue generator to support ongoing R&D operations. Tony has assisted construction companies in developing Request for Equitable Adjustments based on owner caused issues. During that international pandemic, a privately held manufacturer requested Tony and a team quickly manage installation of 3 additional mask lines in a production facility and later two medical grade sponge lines in the same facility. Resource loaded CPM tool, MS Project, was used to successfully fast track and crash the schedule shortening installation and commissioning of the equipment for operational productivity. Tony has set up CAPEX and maintenance processes for a $4B CAPEX spend investor owned company, and trained over 400 of their capital projects team. Tony volunteers for AACE as the Chair of the Energy and Utility Special Interest Group, and formerly for MPUG as the Detroit Chapter President from 2014 to 2018 when MPUG had local Chapter meetings and presentations.

View all articles by Tony Woodrich, PMP, CCP - Certified Cost Professional
Related Content

Continue Reading

Discover more insights and articles that complement your current reading

Collaboration challenges in remote projects (and how to fix each one)
Articles
1 min read

Collaboration challenges in remote projects (and how to fix each one)

Discover 5 common remote project collaboration challenges, from knowledge silos to unclear ownership, and learn practical ways to keep teams aligned and work moving.

A
Anonymous
3 days ago
Read
An Introduction to the PMI Practice Standard for Scheduling Conformance Index
Articles
1 min read

An Introduction to the PMI Practice Standard for Scheduling Conformance Index

Learn how the Conformance Index in PMI’s Practice Standard for Scheduling scores a CPM schedule model, and how to assess its components in any scheduling tool.

A
Anonymous
15 days ago
Read
A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need
Articles
1 min read

A PM’s Halloween Survival Guide: The Sequel You Didn’t Want but Definitely Need

Part II of the PM Halloween survival guide takes on shape-shifting requirements and dependencies that won’t stay resolved, with practical defenses for each.

A
Anonymous
about 1 month ago
Read
Explore All Articles