We use MS Project 2007 Pro and I had this happen to me today. There are resources assigned to the tasks, at least most of the tasks but they are placeholder resources and I don’t think they are the problem, I did not have time to really investigate, so I just over typed the % Complete column on the summary tasks and let it go.