Good Evening Laura,

The 2007 equivalent to the Task Inspector (in Project 2010) is the functionality of Task Drivers
In Project 2007, select a task. On the Project menu, click Task Drivers.

Note you can also keep the Task Drivers open and click from Task to Task.
Enjoy and let me know if you have any additional questions.