Well I’ve kind of answered my own question.  Here is a solution, but it wasnt ideal:-

Remove all work from plan that showed errors

remove the inserted plans

Save as XML

Edit XML file to set silly work/remaining work values to zero

create project from XML

recover views/fields/tables etc.

re-insert plans

check the external links

re-cover work