Sorry Correction
Here is what I found ,
When you want the task to finish the same day, go to options , set the defualt from 8:00 to 5:00 , eneter 9 hours per day , enter 45 hours per week, enter 20 days per month , next go to the calendar , enter 8:00 to 12:00 then 1:00 to 5:00.
otherwise the task will end the next day .
Cheers
“