Reply To: Fixed Duration Task with multiple resources assigned – Task % Completed not reflecting the value

Online Project Management Courses, Lessons, and Live Events | MPUG Forums Discussion Forum Fixed Duration Task with multiple resources assigned – Task % Completed not reflecting the value Reply To: Fixed Duration Task with multiple resources assigned – Task % Completed not reflecting the value

#6795

Joseph,

Good explanation of the issue.  The first thing to note is that % Complete for the task is not an aggregate of % Work Complete.  You also have a % Work Complete for the task which should” be the correct aggregate (assuming both assignments have the same amount of work).  % Complete is a percent of actual/remaining time/duration, and % Work Complete is a percent of actual/remaining work.

There still seems to be an issue with % Complete if a resource has any amount of actual work.  % Complete should show some amount of completion, even if it doesn’t show a true aggregate of work complete.  That may be a bug.  I do know that 2010 still has its share of bugs.  Have you updated to SP1?  That might help.

Hope that helps…