Michael,
You can check the capacity of any selected resources within the Resource Center. Select the resources that make up the generic resource, then click button on the tool bar called Resource Availability. The page will graphically indicate the load and capacity on the selected resources based upon the settings you select (daily, monthly, etc.) as well as indicating which projects will consume their time in future.
Tom