Unfortunately you need to do one more thing. In order to combine the resources you will need a shared resource pool. It’s a bit more than what can be described adequately in an email but basically you would create another project plan that only contains resources and then reference those resources in each of the two projects. I might suggest reading up on it as I said it is a lot for a response.