Reply To: MPP 2010: Importing Excel file issue with Predecessors

Home Forums Discussion Forum MPP 2010: Importing Excel file issue with Predecessors Reply To: MPP 2010: Importing Excel file issue with Predecessors

#6991

Hi Ben – Thanks for the quick reply. I would love to have the PMs use MSP – but that is a whole other topic.

At any rate, what is a workaround for this (so far) is to import the Excel file as needed and then copy/paste the predecessors. This honors multiple assignments as well as leadsa nd lags.

I had also tried to copy/paste the Excel content directly into MSP but it does not retain the outline level, even if that is one of the Excel columns and column order is matched exactly.

Between these two tests and their results, I would say anytihng requiring recognition of the Outline Level won’t happen – as you also indicated.

Regards,