Reply To: Need an MS Project Template for a large Highway & Bridge project

Home Forums Microsoft Project Discussion Forum Need an MS Project Template for a large Highway & Bridge project Reply To: Need an MS Project Template for a large Highway & Bridge project

#10101
Avatar photoCommunity
Keymaster

was available, I would never, ever, use it! To do so would be courting disaster (and quite likely a court action). The only place to start is key deliverables from your contract then entering key components from your drawings and work down from there. For a project like this, you need a professional scheduler to at least get you set up.