Home › Forums › Discussion Forum › 2 Tasks, 1 Project; Task A is not by working days but Task B is working days
Task A lasts X long (24/7 scheduling)
Task B lasts Y long (working days only)
Griffin
Not sure what the question is, but I’ll assume its how to do this.
Define your normal work calendar, for example, M-F 8-5. Make that the project calendar and by default, Task B will use that calendar since you didn’t override it at the task level.
Create a 24×7 calendar and on Task A, attach that 24×7 calendar to that task.
Hope that helps
Daryl,
I realized I didn’t put an ask of any sort, thank you for decoding my post! Very helpful!