Home › Forums › Microsoft Project Discussion Forum › Auto assigment of resources
Dear All,
I would like to kindly ask you to help me with below situation
On Grant Chart I made up column where I have formula. According to this formula the column shows me how many person I need to complete the task till Deadline.
Is there any possibility to set up RULE, Function and etc. where MS project will take numbers from this column (let’s say NUmber10) and add resources to this task?
Thanks a lot in advance
Kindly
Ramil G
You might be able to try something with VBA.
Dear Larry,
Thanks a lot for reply.
Please correct me if I am wrong but I think this option available in higher version of MS projects. I am using MS 2010 and there is no DEVELOPER tab to check VBA. Or might be I can look VBA on different area?
Thanks a lot in advance
Have a nice week-end
To activate the Developer ribbon, go to File / Options and select the Customize Ribbon tab. You can then select to display the Developer ribbon. Hope that helps…