Auto assigment of resources

Home Forums Microsoft Project Discussion Forum Auto assigment of resources

Viewing 3 reply threads
  • Author
    Posts
    • #397097
      Ramil Ganiyev
      Guest

      Dear All,

      I would like to kindly ask you to help me with below situation

      On Grant Chart I made up column where I have formula. According to this formula the column shows me how many person I need to complete the task till Deadline.
      Is there any possibility to set up RULE, Function and etc. where MS project will take numbers from this column (let’s say NUmber10) and add resources to this task?

      Thanks a lot in advance
      Kindly
      Ramil G

    • #397099
      Larry Christofaro
      Participant

      You might be able to try something with VBA.

    • #397100
      Ramil Ganiyev
      Guest

      Dear Larry,
      Thanks a lot for reply.
      Please correct me if I am wrong but I think this option available in higher version of MS projects. I am using MS 2010 and there is no DEVELOPER tab to check VBA. Or might be I can look VBA on different area?

      Thanks a lot in advance
      Have a nice week-end

    • #397101
      Larry Christofaro
      Participant

      To activate the Developer ribbon, go to File / Options and select the Customize Ribbon tab. You can then select to display the Developer ribbon. Hope that helps…

Viewing 3 reply threads