  • #416700 Reply
    Robert
    Guest

    Hi

    My projects don’t seem to be adjusting or changing to the dates/duration inputted. If I change a duration or start date none of the successors move, only the line I’ve amended. I’ve tried creating new projects and adjusting old ones but it’s still not working, however if I send my project to a colleague they have no issues adjusting theses elements.

    What button/check box am I missing please?

    Thanks

    #416701 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Hi Robert. It appears that the issue is not related to manually scheduled tasks since it works for others. Try looking at the Calculation option and make sure that project calculates after each edit. The option is in the Calculation section of the Schedule tab in Options. My guess is that somehow got set to Off. Hope that helps…