I have read what I can on the topic of MCPs but I am not confident the information out there is complete. My understanding is that to view MCPs in a single schedule (no inserted projects), that the path will drive to each open successor. Therefore, with MCP turned on, if I have 4 independent workstream schedules and want the MCP for each, I will need 4 empty successors (final task per workstream). Is there more to this?
Debra, that is basically the feature. Are you seeing a specific behavior that you feel is incorrect? Let me know if you have a specific situation that doesn’t work the way you expect it to and we can help out. Thanks…