Home Forums Discussion Creating project inputs in hours rather than days

This topic contains 1 reply, has 2 voices, and was last updated by Jigs Gaton Jigs Gaton 2 months, 2 weeks ago.

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #414162 Reply

    Liz

    Is it possible to create inputs in hours and how would you do this in MS Project please?

    #414163 Reply
    Jigs Gaton
    Jigs Gaton
    Member
    • Author
    • Forum Pro

    Liz, yes you can enter hours in many ways, and in many different places. Easiest? Just type Xh in the Duration column where X=hours, or do the same wherever you see the Work column. For example, using Task Details you can have a duration of 1 day, but assign resources to the task in hours (ie. me = 4h, you = 4h). Hope that helps!

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Creating project inputs in hours rather than days
Your information:




9 + 1 =