Loading...
Quick Links

Custom Field Not Showing in Resource Assignments

Home Forums Discussion Custom Field Not Showing in Resource Assignments

Viewing 12 posts - 1 through 12 (of 12 total)
  • Author
    Posts
  • #31722 Reply
    Lisa Barnes
    Participant

    We created an Enterprise Custom Field (we call Activity ID) in Project Server 2010 because it helps us to track/identify our Tasks in our projects.  This Activity ID field works fine when looking at each project’s tasks in the Project Center in Project Web App.  But when we use the Resource Assignments screen in Project Web App to look at our task resource assignments, this custom field is completely blank.  It is also not available in the tasks under ‘My Work’.  We don’t know why we can see it in the Project Center, but yet it is not present in Resource Assignments or My Work?
     

    #31728 Reply
    E. M. Hanna
    Guest

     
    The reason that your field is blank is that you are looking at a different field.  You appear to have created a task-level ECF and have populated it and used it to good advantage in task-level views.  However–on the Resource Assignments view, you are looking at assignment-level ECFs.  The ECF has the same name–but it is a different field.
     
    You can roll down task and resource custom fields to assignment level. On the New Custom Field or the Edit Custom Field page in Project Web Access, click Roll down, unless manually specified in the Calculation for Assignment rows section.
     

    #216827 Reply
    Jay Lartey
    Guest

    in PWA i am trying yo Manage Views for exmaple Monthly Task Overiew, when i create the report i can see the Cost per task, i dont want to see the cost per resources as the cost varies, How can i get “Fixed Cost” to show when i create a report in PWA (Project Web App)?

    #409618 Reply
    AJ de Wet
    Guest

    Hi E. M. Hanna, I did click on Roll down as suggested by your post on 10/02/2013, but the Resource custom fields do not show up in a Resource Assignments view. Any other suggestions? I found one field that shows, so I created a duplicate field (different name) with the exact same settings (Roll down etc.), but it doesn’t show up? Is there any other custom field setting or assignment rule that has to be in place before the custom resource fields will show up in the Resource Assignments views?

    #411037 Reply
    Mohammad
    Guest

    Hello,

    The custom field not appear on Notification Email when create a task, Help me please.

    Thanks in advance.

    Regards,
    Mohammad

    #488778 Reply
    Linda Kevin
    Guest

    The same goes for me, I couldn’t find the given assignment. Can anyone help me out? I recently bought a custom Dissertation and it’s not publishing on my project server.

    #502294 Reply
    David John
    Guest

    Are you looking for assignment services that is cheap and reliable. GlobalAssignmentHelp is one of the top assignment services providers, where every student can easily opt our services at cheap Assignment Help Price. So don’t waste your time and start taking consultations from our expert writers.

    #503015 Reply
    jang dong
    Guest

    You can play Slope Unblocked free here. You’ll need to steer your ball using the arrow keys, while taking care to avoid obstacles and not bump into red walls.

    #507069 Reply
    Josh Martin
    Participant

    There are so many writing services out there, and while some are legitimate and others are not, I can confidently tell that I have never seen a low-profile business. I’ve used a few writing services for taking online ASp.NET Assignment Help and for essay help, and now I go to Assignment Prime whenever I need assignment help, and they create my assignment completely unique and instructive. The finest thing is that they provide assignment writing service in very low cost.

    #507216 Reply
    Marins
    Guest

    Trial testing is necessary once the proposal has been written and a cv writing services uk has been chosen in order to determine the error margins. These inaccuracies therefore hint to the study’s weaknesses. The writer’s fault of preparing the proposal in chronological order is one that should be avoided if at all feasible.

    #516774 Reply
    candymika
    Participant

    Interesting topic for a blog. I did an interesting search on the Internet and came across your site. Great post. Thanks so much for sharing your knowledge! It’s great to see that some people still put in the effort to manage their websites. I’ll definitely be doing a reality check soon.retro games

    #520407 Reply
    MaksRomanov
    Participant

    people, please tell me why people try to write an essay themselves when there is an essayist (college paper help) who can write everything for you, you just need to contact them!! why extra problems, explain to me, maybe I don’t understand something?

Viewing 12 posts - 1 through 12 (of 12 total)
Reply To: Reply #516774 in Custom Field Not Showing in Resource Assignments
Your information: