Embed Project schedule into a Word document

Home Forums Microsoft Project Discussion Forum Embed Project schedule into a Word document

Viewing 1 reply thread
  • Author
    Posts
    • #116343
      Fred S
      Guest

      Is there a way to embed a Project schedule into the body of a Word document? Can the embedded file be scaled up or down to fit a specific window size?

    • #116349

      Fred,

      Once you’ve selected the view that you’d like to use, the quickest way is to use MS Project’s “Copy Picture” feature. On MSP 2010 it located on the ribbon under tasks. Then place your cursor in Word document location and select Control V to paste. You can quickly resize by grabbing one of the circled spots on the graphic. For other resizing options, place your mouse on the graphic and press the right mouse button. On the pop up menu, select size and position.

      Ken