Project 2010 recognizes that weekend’s aren’t work days. None the less, in the particular case of if I set an activity as lagging 14 days behind another one, I want it to include non-work days within that lagtime (as the deadline of 2 weeks includes work and non-work days). Is there any way to have MS Project recognize that lag time should include all days, not just work days?
I’m new to MSProject, but I believe (in 2013 at least) you use Edays in the lag time instead of days (Edays refers to Elapsed Days and includes the days off)