Home Forums Discussion Having Project Not Include Non-Working Days in Lag Times?

This topic contains 4 replies, has 4 voices, and was last updated by  Achini 2 weeks ago.

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #377219 Reply

    daniel
    Member

    Project 2010 recognizes that weekend’s aren’t work days. None the less, in the particular case of if I set an activity as lagging 14 days behind another one, I want it to include non-work days within that lagtime (as the deadline of 2 weeks includes work and non-work days). Is there any way to have MS Project recognize that lag time should include all days, not just work days?

    #377229 Reply

    I’m new to MSProject, but I believe (in 2013 at least) you use Edays in the lag time instead of days (Edays refers to Elapsed Days and includes the days off)

    for 2 weeks you could put 14ed or 2ew

    #377243 Reply
    Larry Christofaro
    Larry Christofaro
    Participant
    • Expert
    • Forum Pro
    • Ombud

    Ken is corect, and available in any version (at least in this century…). The format is 1FS+14 ed (successor to task 1, FS, plus 14 elapsed days).

    #377678 Reply

    daniel
    Member

    Thanks!

    #415268 Reply

    Achini

    Can we add elapsed hours in a similar way so that the lag time can be entered in elapsed hours?

Viewing 5 posts - 1 through 5 (of 5 total)