How can I highlight days on the time scale with out making them non working days

Online Project Management Courses, Lessons, and Live Events | MPUG Forums Discussion Forum How can I highlight days on the time scale with out making them non working days

Viewing 1 reply thread
  • Author
    Posts
    • #113099
      Garry
      Guest

      Hi All

      How can I highlight certain days, as appears with non working days, on the time scale. I would like to highlight certain days + weeks in which certain tasks nee to be competed + it would be of great benifit if I could see that in the gantt.
      thanks a million.

    • #114280
      Larry Christofaro
      Participant

      Unfortunately your specific item can’t be done. You can setup deadlines to indicate days that certain tasks need to be complete.

Viewing 1 reply thread
  • You must be logged in to reply to this topic.