I added 4 custom cost columns, one of which show the total of 3 others. How can I transfer data from that customized column to fixed cost column for the 300 tasks of my project. Thanks for your help! Guy
Guy, you should be able to copy the entire total cost column and then select and paste it to the Fixed Cost column. Hope that helps…