How to automatically adjust task duration

Home Forums Discussion Forum How to automatically adjust task duration

Viewing 0 reply threads
  • Author
    Posts
    • #541313
      guy forget
      Participant

      I use Ms-Project 2019, I have 3 linked tasks one after the other 2.
      I want the duration of the second to automatically adjust according to the end of the first and the start of the third. Ex: I have 3 tasks of 1 day, I want that if the third task should start 2 days later than planned, that the second goes from 1 to 3 days.
      In summary: The duration of task 2 automatically adjusts according to the end of task 1 and the start of the third.
      How to do?

Viewing 0 reply threads
  • You must be logged in to reply to this topic.