How to display “% Complete” value field for tasks on Timeline view ?

Home Forums Discussion Forum How to display “% Complete” value field for tasks on Timeline view ?

Tagged: 

Viewing 0 reply threads
  • Author
    Posts
    • #566276
      Marcos Berenguel
      Participant

      The Timeline view is based on project data from Gantt Chart view.

      The mouse hovering on task in Timeline view display the value for “% Complete” and other information.

      I need to show in Timeline view the “% Complete” value field beside of “Finish date” or any other position inside the task as other information displayed.

      Does anyone know how to do that, please ?

Viewing 0 reply threads
  • You must be logged in to reply to this topic.