I have a project and I faced the problem that I couldn’t solve!
I added my tasks and assigned my resources to them and there are some overallocated resources!
and the problem is here:
I Level resources automatically and save the project and exit Microsoft Project! then I open it again and the resources are overallocated again!
and I don’t know what should I do about it?
I search and I ask a lot of people, but they don’t know how to solve this.
Javad, hard to tell what the issue is. Does the project change when it is closed and open again? Are the resources really over-allocated or is it the over-allocation indicator? Just trying to get a better understanding of the issue. Thanks…
When you have levelled the resources try making another change to the plan; add a dummy task at the end with no resource. See if this saves. If it does then you at least know that MSP is actually saving the plan and you only have to work out why levelling is being removed.