Home › Forums › Microsoft Project Discussion Forum › Info Ms-Project to Google Calendar
I am using Ms-Project version 2019 and I would like to have the possibility of informing the resources of the tasks (name of the task and the date) to which they have been assigned, and this in a Google calendar. If the date changes in Ms-Project it should also change in the calendar.
How to do?
Guy —
Sorry, but this is not possible to do with any version of the Microsoft Project desktop application. Hope this helps.