Linking Summary Tasks as External dependencies.(predecessor)

Online Project Management Courses, Lessons, and Live Events | MPUG Forums Discussion Forum Linking Summary Tasks as External dependencies.(predecessor)

Viewing 1 reply thread
  • Author
    Posts
    • #5244

      I know it is not good practice to link summary tasks. But I have a situation. One of the summary task is an external predecessor to my task on a project. The task I am trying to link uses the “start and finish dates” from the summary task in another project. My question is:

      Can I link the summary task as an external predecessor to a task in another file?

       

      Thanks

    • #9735

      Hello asimansari,

      It is not a good practice as any external linking can lead way to file corruption.

      If I read your post correctly you are needing to use both the start and finish dates from one schedule in another.

      This can be accomplished by going to the start and finish cells of the task you want to use the start finsh date, copy these cells and go to the task in the file and cells where you want to use these dates, click in the cell and right click and paste special, and select link. These dates should now change in the copied file when ever you change them in the file from whence they were copied.

      Cheryl

Viewing 1 reply thread
  • You must be logged in to reply to this topic.