MS Project 2016

Home Forums Discussion Forum MS Project 2016

Viewing 0 reply threads
  • Author
    Posts
    • #417252
      NZ
      Guest

      1- Is there a column option for “material” to track quantity based progress
      2- if we enter cost it calculates correct CPI, however SPI is off, because it is linked with duration and percent complete, please advise!
      3- once we clear the original baseline and reassign the baseline, bars doesnot show the baseline with black line.

      All above questions are may b basic, however i am facing lot of difficulties to resolve them. Please advise